ED 1 and AHIP: 100 percent affordable housing in Los Angeles

Entitlement, Los Angeles. By Lucas Rebouças, Founder & Principal, TECTO GROUP. Code text verified 28 October 2026.

A project whose units are all restricted affordable has two City pathways in Los Angeles: the program of LAMC 12.22 A.40, which codifies Executive Directive 1 (ED 1), and the Affordable Housing Incentive Program (AHIP) of LAMC 12.22 A.39. Both reward the full set-aside with incentives on height, floor area and the development standards, and both keep the approval administrative where the project stays within their limits.

What the pathway permits

A.40 was added by Ordinance 188,788, effective 19 December 2025. A project electing it receives up to five incentives, on or off the City menu, and one waiver of a development standard. Off-menu requests are capped: in a residential zone, height may rise by up to three stories or 33 ft over the zone's limit; in any zone, open space may drop by up to 50 percent, bicycle parking by up to 50 percent and tree planting by up to 25 percent; in a commercial zone, the ground story requirements may drop by up to 30 percent. The program's performance standards cannot be waived.

AHIP (A.39) serves 100 percent affordable projects of five or more units, and also Public Land, Faith-Based Organization and Shared Equity projects at 80 percent restricted. Its base incentives and its on-menu additional incentives are processed by the City in plan check.

Where it applies

How approval works

Under A.40, City Planning approves the project through Expanded Administrative Review for compliance with objective standards: no hearing, no appeal, and the approval is not a project under CEQA. The ED 1 Implementation Guidelines set a completeness review within 30 days and a decision within 60 days of a complete application; A.40 itself states no day count.

Under A.39, a request beyond the menu goes to Expanded Administrative Review; up to three waivers go to a Director's Determination, appealable to the City Planning Commission; more than three waivers follow the Class 3 Conditional Use procedure before the Commission, whose decision is final.

On either pathway, the Los Angeles Housing Department records the affordability covenant before the building permit issues, and the building permit follows in plan check.

What to check on a site

Questions

Is ED 1 still in effect in Los Angeles?
Its approval procedure is codified in LAMC 12.22 A.40 (Ordinance 188,788, effective 19 December 2025). Projects that elect A.40 are reviewed under it.
Does an ED 1 project need a public hearing?
No. A.40 approval is Expanded Administrative Review for compliance with objective standards, with no hearing and no appeal, where the project meets every eligibility condition.
Can a site with rent-stabilized units use ED 1?
A parcel with 12 or more RSO units occupied in the prior five years is excluded. On a smaller site the RSO units are replaced.

Sources

These guides summarize the code text for general information and are not legal advice. Every site is read under the code, the overlays and the ordinances that apply to it on the day of preparation.

TECTO GROUP takes multifamily sites through these pathways for owners, from the first study through entitlement and design to a permit ready to issue. Send the address of the site under consideration.