The Live Local Act in unincorporated Miami-Dade County
For counties, the Live Local Act is Fla. Stat. 125.01055(7). The County may not require a rezoning, a land use change, a special exception, a variance or a plan amendment for the height, zoning and density the statute authorizes, and it approves a qualifying project administratively. The provision expires on 1 October 2033.
Where it applies
- Land zoned commercial, industrial or mixed use; in the County's reading, BU, IU, RU-5, RU-5A and planned districts that allow those uses.
- Land owned by the County, a municipality or the school district, with the owner a party to the application, or more than 3 acres owned by a religious institution with a house of worship for 10 years or more.
- At least 40 percent of the units rental and affordable (Fla. Stat. 420.0004) for 30 years; a mixed-use project at least 65 percent residential.
Exclusions
Airport-impacted areas under Fla. Stat. 333.03(5), unless the airport's governing body approves; the Everglades Protection Area; areas of critical state concern; conservation easements; and land within a quarter mile of a military installation, among others.
How approval works
Every Live Local application goes through the County's Administrative Site Plan Review, where concurrency, traffic, landscaping and airport zoning still apply; a decision is appealable to the Community Zoning Appeals Board. The 30-year affordability is secured by a recorded restrictive covenant and an annual report. Demolition of an existing structure for the project is administrative.
Questions
- Does a Live Local project in unincorporated Miami-Dade need a public hearing?
- No. It is approved administratively through Administrative Site Plan Review; a hearing arises only on an appeal to the Community Zoning Appeals Board.
Sources
These guides summarize the code text for general information and are not legal advice. Every site is read under the code, the overlays and the ordinances that apply to it on the day of preparation.
TECTO GROUP takes multifamily sites through these pathways for owners, from the first study through entitlement and design to a permit ready to issue. Send the address of the site under consideration.